Projects - 1993

 

Project: Pak N Save #3124, Manteca, CA

Type: New Fixture Installation

Architect: Safeway Design Dept.

Contract Amount: $159,500

Completion Date: 02/07/93

 

Project: Sizzler Restaurant, Walnut Creek, CA

Type: ADA Access Remodel

Architect: S.J. Sung & Associates

Contract Amount: $142,500

Completion Date: 04/01/93

 

Project: Burlington Coat Factory, San Francisco, CA

Type: Remodel

Architect: S.J. Sung & Associates

Contract Amount: $103,000

Completion Date: 05/25/93

 

Project: Sal's Deli, San Mateo, CA

Type: Tenant Improvement

Architect: S.J. Sung & Associates

Contract Amount: $56,000

Completion Date: 06/17/93

 

Project: Safeway #279, Jackson, CA

Type: Remodel

Architect: S.J. Sung & Associates

Contract Amount: $287,500

Completion Date: 08/15/93

 

Project: Safeway #993, Fremont, CA

Type: Remodel

Architect: S.J. Sung & Associates

Contract Amount: $50,000

Completion Date: 09/01/93

 

Project: Burlington Coat Factory, San Jose, CA

Type: Remodel

Architect: Burlington Coat Factory

Contract Amount: $125,000

Completion Date: 09/01/93

 

Project: Pak N Save #3128, Stockton, CA

Type: Remodel

Architect: Safeway Design Department

Contract Amount: $370,000

Completion Date: 10/24/93

  

Project: Jack in the Box, Various stores, Northern CA

Type: ADA Upgrade Remodels

Architect: Foodmaker, Inc.

Contract Amount: $60,000

Completion Date: 12/01/93

 

Project: Three Waters Park Office Building, San Mateo, CA

Type: Tenant Improvement

Architect: S.J. Sung & Associates

Contract Amount: $75,000

Completion Date: 12/23/93